2018 Street Resurfacing Project Moves toward Cornhusker Road and Cedar Island Road

Cornhusker Road milling and paving operations will take place at night from 7:00pm to 7:00am

  • 17 August 2018
  • Author: Phil Davidson
  • Number of views: 6116
  • 0 Comments
2018 Street Resurfacing Project Moves toward Cornhusker Road and Cedar Island Road

As the City of Bellevue’s 2018 Street Resurfacing Project moves towards Cornhusker Road and Cedar Island Road, the City of Bellevue's Public Works Department has released an updated tentative schedule for these areas. This newly updated tentative construction schedule shows the projected dates for milling and paving operations as well as the dates that road closures will be necessary to complete improvements. Maps and Detour information is provided with this article. The City of Bellevue is working with the contractor to minimize the inconvenience to motorists and businesses in the area as much as possible and the cooperation and patience of the public is appreciated as these much needed road improvements are completed.

Here are some notes regarding the next phase of the 2018 Street Resurfacing Project

  • Utility adjustments will begin on Lincoln Road and Harvell Drive on Thursday, August 23rd
  • Cornhusker Road milling and paving operations will take place at night from 7:00pm to 7:00am
  • Cornhusker Road lane closures will remain in place during the day
  • The Kennedy Freeway southbound and northbound off-ramps will have short term closures during the first two nights of paving (tentatively scheduled for 8/23 & 8/24)
  • Construction will be coordinated to avoid directly impacting traffic heading to and from the Bellevue West football game and volleyball tournament on Friday, August 24th
  • Street Closures will not be required on Cornhusker Road; however, lane closures will be required during this process

 

2018 STREET RESURFACING PROGRAM

TENTATIVE CONSTRUCTION SCHEDULE

DATE

MILLING OPERATIONS

PAVING OPERATIONS

No Street Closures Required
(under traffic with flaggers)

Street Closures Required

August 16, 2018

Thursday

36th Street/Cedar Island Road

 

August 17, 2018

Friday

Cedar Island Road

Chandler Road

August 18, 2018

Saturday

 

Chandler Road/36th Street

August 19, 2018

Sunday

 

 

August 20, 2018

Monday

 

36th Street

August 21, 2018

Tuesday

Cornhusker Road (night)*

Cedar Island Road

August 22, 2018

Wednesday

Cornhusker Road (night)*

Cedar Island Road

August 23, 2018

Thursday

Cornhusker Road (night)*

Cornhusker Road (night)*

August 24, 2018

Friday

Cornhusker Road (night)*

Cornhusker Road (night)*

August 25, 2018

Saturday

 

 

August 26, 2018

Sunday

Cornhusker Road (night)*

Cornhusker Road (night)*

August 27, 2018

Monday

Cornhusker Road (night)*

Cornhusker Road (night)*

August 28, 2018

Tuesday

 

Cornhusker Road (night)*

August 29, 2018

Wednesday

 

Cornhusker Road (night)*

Note:  Utility adjustments to follow Paving Operations (under traffic with no Street Closure)

* Street Closures will not be required; however, Lane Closures will be required.

 

The resurfacing program is one of the most visible programs the City undertakes each year and is 80% funded through the State program.  Through this program the City resurfaces and repairs streets damaged by age, freezing and thawing, and other factors.  Generally, the work will consist of milling off 2” of the existing surface, and laying down a new asphalt surface course.  This new surface is smooth and will extend the life of the street. Utility adjustments of manholes, valve boxes, and inlets will be completed once milling and resurfacing. 

As with all roadway construction activities, this work may cause an inconvenience to you.  The public is asked not to move or otherwise tamper with barricades or other warning devices.  They are the primary mechanism for identifying potentially unsafe conditions. 

Print
Categories: Announcements
Tags:
Rate this article:
No rating

x

Archive